The work is in full swing at the stadium in Lubin

The work is in full swing at the stadium in Lubin

Published 28 October 2009

The Lubin Stadium is still in a centre of attention of residents of the region. Every month many letters comes with the questions about another stages in the project. Football fans know the designer’s idea of emphasizing three colours of Zagłębie club with the use of building elements, which is: orange chairs, a white roof and a green turf. All interested people are asking in their emails about assembling the chairs on the fourth stand in order to complete a lack of an orange colour.

The first seats will already appear in the beginning of December – says Piotr Fedoszczak,
a site engineer and a leader of Consortium acting on behalf of PeBeKa – At this moment we are almost finishing the canopy roof above the fourth part of the stands. Installation works are done at full steam as well as thermal insulation of club building, execution of roads and sites, toilet foundations or first aid points.

About two third of the conopy roof has been executed and there is still a part of the sheets to be installed between the host fun club sector and the club building. After finishing the assembly of troughed sheets the company will set about flashing finishing the scope of works.

An expanded polystyrene was sticked on the south side of the building and soon the works will start on the west wall of the building allowing the other crew to plaster and paint the building.

At the same time some roads and sites are executed together with indispensable road base consisting of the bound, backing and drainage layers ended by road paver. The whole road works include pedestrian ways under the stands, access roads and pavements, parking lots for cars, coaches and also for recording vans. According to the first project one part of the site, after dismantling of stands earth bunds, will be used for additional parking places for  VIP and Super VIP fans and for club administrative employees.

Because of levelling the earth bunds the constractor meet the challenge to haul away
a hundred and twenty thousand cubic meters of earth. Dismantling is carried out on either side at the same time.

In the main building some complex works are now in progress, such as: electrical and sanitary works, waterworks, air conditioning and monitoring works, which are invisible from outside.